Buckinghamshire County Council

Project > Buckinghamshire County Council

Size > 7 x Pre-school & Children Centres

 

Download

 

Buckinghamshire County Council

 

Project Details >

 

7 x Pre-school & Children Centres
Single storey
Cladding: Various: - Cedar, Brickslip or Render
Factory build: Typically 6 weeks
Installation: 1 days
On site: 2 weeks

Buckinghamshire County Council image 1

 

 

 

Britspace has completed a contract to provide 7 Pre-school Centres and Childrens Centres for Buckinghamshire County Council.

Each building has been individually designed to suit the needs of each school and of the local planning offices.

The buildings were manufactured and fitted out at our factory in East Yorkshire whilst the foundations were prepared by the Council’s own contractor.

The buildings were erected over a weekend and completed in just 2 weeks, ready to occupy.

 

Buckinghamshire County Council image 2

 

 

Buckinghamshire County Council image 3