Pontefract General Infirmary

Project > Pontefract General Infirmary

Size > 1000m²

 

Download

 

Pontefract General Infirmary

 

Project Details >

 

Two storeys
Cladding: Fairface block & Rainscreen Cladding
Factory build: 10 weeks
Installation: 3 days
Overall Programme: 16 weeks

Pontefract General Infirmary image 1

 

 

 

Britspace constructed a two storey facility for Mid Yorkshire Hospitals NHS Trust at Pontefract General Infirmary.

The building houses the Diabetes Clinic and also provides offices and training facilities for the Trust.

The elevations in fairface block and rainscreen cladding faithfully reflect the architects design.

Britspace provided a turnkey package including foundations as part of the enabling works for the Mid Yorkshire Hospitals PFI, which involves a major redevelopment of the site.

 

Pontefract General Infirmary image 2

 

 

Pontefract General Infirmary image 3